Project Plan:  A timetable for completion


 

For up-to-date events see also: Progress Diary
 
  Nov-Dec '06 Completion of Major Construction Works
  June '05 Construction
  Apr '05 Laying of Foundation Stone.
  Feb - Mar '05 Procurement - Tender Period
  20th Feb '05 Roz-e-Ashura
  Jan '05 Structural & Mechanical Design, H & S
  Dec '04 Plans submitted for Building Regulation approval - Inshallah.
  Oct '04 Main Planning Permission granted.
    Sept '03 Main Planning Permission application submitted to Council.
  June 02 Outline Plans approved by Council.
  May 02 Architect employed.  Outline Plans drawn. Plans passed by Leicester Jamaat Members. Plans submitted to Council.
  13th Rajab Keys to Duxbury Road given to Al-Husseini Building Project.
  Jan '01 Placed offer on former Avalon Centre, Duxbury Road.
  Mar '99 National and International Fund raising for new plot begins.
  Feb '99 Gained Ijaza to utilise Khums from all leading Marja, see here.
  Feb '98 Search for new plot begins.
  Feb '98 Meeting with Marhum Mulla Asghar.  Achieved support from World Federation for the project, see here
  14th Feb '98 Decision to purchase new land or premises on which to build a purpose built mosque.

Al-Husseini Building Committee elected.



 

 